April 24, 2015
City of Prescott
Park Avenue Improvements Project

Welcome to the City of Prescott Park Avenue Improvements Project eNews. Motorists and residents are reminded to call the Project Hotline at 541-7825 to speak to a project team member about any questions or concerns.


DETOUR ROUTES

The current barricade closure at Glenwood Avenue will remain in place. Park Avenue is closed between Hill Avenue and Copper Basin Road.


PAVING TO BEGIN

Paving operations are scheduled to begin Monday, April 27 and continue throughout the week on Park Avenue between Gurley Street and Copper Basin Road.


ROAD GRADING CONTINUES

Crews continue to grade Park Avenue between Glenwood Avenue and Canyon Springs Road. Summit Avenue south of Gurley Street through Glenwood Avenue to Park Avenue will remain closed. Normal traffic operations will be restored during non-work hours. Delays can be expected. Local traffic will be permitted.


CURB AND SIDEWALK INSTALLATION

Curb and sidewalk installation on Park Avenue will occur throughout the week from Canyon Springs Road south to Bertrand Avenue and from Glenwood Avenue to Country Club Drive.

Please be aware of the following impacts:
  • Monday, April 27, through Friday, May 1, from 7:00 a.m. - 5:30 p.m.
    Changing lane configurations, flagging operations, and traffic stops will occur within the project corridor. Use alternate routes whenever possible.



  • The City of Prescott and Fann Contracting greatly appreciate cooperation from the community and parents of Lincoln School students during the Park Avenue Improvement Project. The City thanks you for your understanding during construction.

    Click HERE to view the Phase Two Detour Map


    Please note: In the event of equipment failure or inclement weather, the work schedule may be altered or suspended without notice.

    The 24-hour Project Hotline can be reached by calling 541-7825 for more project info.